This project involves the design and construction of two data centre buildings and accompanying substations, on a 15.7-hectare site south of Paris. The site backs onto a highway and is crossed overhead by several high voltage lines. Construction of the first phase, comprising the first data centre building and substations, began in 2023 and was completed in 2024, with the fitout beginning in 2024 and finishing in 2025. The second building starts construction in autumn 2024 and will be delivered in 2026.